Council, Features

Expected Traffic Disruption – March – Aug 26

The Parish Council would like to alert residents to some significant roadworks that are due to commence on 28 March 2026, affecting the A361 and Ells Lane.
Power On, RCE and GTC, working on behalf of the National Grid, are laying power cables from the primary substation on Ells Lane through to Bodicote, in support of a housing development on Bankside.
This will involve traffic controls on the A361 from Ells Lane to Wykham Lane and phased road closures of Ells Lane and Wykham Lane for different periods until August 2026.
As the A361 is the main arterial route through the village, it is expected there will be traffic disruption during the works.
The anticipated project timeline is as follows
Location Nature Work Commences Work Ends Days Affected
Elts Lane junc Banbury Road (Wyatts to A361) Bloxham Multiway lights 28/03/2026 12/04/2026 13
Molyneux Drive Bodicote Multiway lights 30/03/2026 26/04/2026 27
Bloxram Road (A361 to Wykham Lane) Bloxham 2-way & multiway lights 10/04/2026 26/05/2026 46
Broad Gop Bodicote 2-way & multiway lights 13/04/2026 10/05/2026 27
Weeping Cross Bodicote Multiway lights 13/04/2026 03/05/2026 20
Oxford Road Bodicote Multiway lights 27/04/2026 28/05/2026 31
High Street Bodicote Multiway lights 01/05/2026 17/05/2026 17
Ells Lane (Wyatts to Primary Station) Bloxham Closure 18/05/2026 28/06/2026 41
Wykkham Lane Bloxham Closure 20/05/2026 09/08/2026 90
The Parish Council is actively engaging with the contractors and Oxfordshire County Council to minimise disruption.
Updates on the progress of the project will be published he Parish Council website as they are received.